Suspense. Tension. Bellefonte!

house near bellefonte I’m not sure if it belittles the importance of the event to call it, well, suspenseful:

Later this month [this Friday, to be exact], the board of the Tennessee Valley Authority could take up a proposal to complete the Bellefonte nuclear power plant in northeast Alabama.

TVA administrators are conducting a campaign to gain public support for the project and nuclear energy in general despite a dangerous incident at a Japanese plant this year.

TVA had already put off making this decision once:

TVA staff says the most reliable and least costly option for future growth in electricity needs is nuclear power and completing the Bellefonte plant in Hollywood, Ala., for an estimated $4 billion to $5 billion. The board’s vote on the proposal, which had been expected this past spring, was put off after a nuclear fiasco in Japan.

“Dangerous incident,” “nuclear fiasco.” We may in for a long period of creative description-making for the accident at Fukushima. I’m not crazy about either of these,but points to reporters for mixing it up a bit.

With costs rising and more regulations anticipated for TVA’s aging coal-fired plants — the historic workhorse of electricity generation — the nation’s largest public power producer stands at a crossroads as the meeting approaches.

Oddly, the story doesn’t mention why aging coal plants might be facing rising costs and more regulation. Nuclear facilities are not exactly regulation free, after all. In any event, it’s clear that writer Anne Paine is feeling the suspense, too:

None of the board members contacted by The Tennessean last week was definite on how he or she would vote on Bellefonte.

Three members — [Barbara] Haskew; Mike Duncan of Inez, Ky.; and William Sansom of Knoxville — did not return telephone calls for comment. Those reached talked about keeping rates as low as possible for the9 million people served in parts of seven states through TVA’s distributors.

That actually speaks well to approving Bellefonte, but that’s what you do when you can’t know: you read teas leaves – parsing what people say for a hint.

There has been, as you might expect, some criticism from an environmental coalition called the Southern Alliance for Clean Energy (SACE). Some groups put up good contentions that ought to be answered carefully, but SACE just cooked up a stew of issues that aren’t really issues.

SACE released a report, saying TVA should not go forward at Bellefonte, providing what they claimed seven major factors that say TVA's attempt is extremely costly and and dangerous.

Here’s a bit from SACE’s press release:

Efforts by the Tennessee Valley Authority (TVA) to resume construction at the long-shuttered, nearly forty-year-old Bellefonte nuclear reactor Unit 1 in Jackson County, Alabama, are unlikely to be successful due to seven major problems, including water damage to the reactor site foundation, compromised radiation containment in the unfinished reactor, and a lack of records about what exactly went on when the critical systems in the unfinished plant were cannibalized while the project lay dormant.

Which makes it sound as though TVA intends to walk into the plant as-is and flip a switch.

[TVA President and CEO Tom] Kilgore said a completed Unit 1 at Bellefonte would essentially be a new unit, using the latest equipment and technology to meet the latest safety standards and regulations.

He also talks about the “water damage” – there isn’t any. Of course, if SACE cannot be sure of Bellefonte – as it presumably cannot – that provides a lot of license to promote what must be true or, to put it more specifically, what SACE feels must be true. And that’s being generous.

Unless the TVA board hangs onto its votes for awhile without revealing them – the vote itself is secret – we should know if TVA will be going ahead with Bellefonte this Friday.

Oh, the suspense.

---

If Bellefonte is approved, the plan currently is to bring it online in 2018, which means it will have taken 44 years from conception to completion. The project was officially suspended in 1988 due to falling energy costs, with reactor 1 about 88 percent complete. Reviving the project has percolated for awhile now and in 2008, TVA asked the NRC to reinstate the construction permits, which has happened. The recession depressed (recessed?) the demand for more electricity, so the original 4-reactor project is now one – well, one for now. Here are some up-to-date TVA talking points about Bellefonte.

On the road to Bellefonte – you didn’t really want another shot of a plant, did you? You can see a cooling tower over the trees on the left. It’ll be nice if they actually get to cool something.

Comments

Popular posts from this blog

An Ohio School Board Is Working to Save Nuclear Plants

Ohio faces a decision soon about its two nuclear reactors, Davis-Besse and Perry, and on Wednesday, neighbors of one of those plants issued a cry for help. The reactors’ problem is that the price of electricity they sell on the high-voltage grid is depressed, mostly because of a surplus of natural gas. And the reactors do not get any revenue for the other benefits they provide. Some of those benefits are regional – emissions-free electricity, reliability with months of fuel on-site, and diversity in case of problems or price spikes with gas or coal, state and federal payroll taxes, and national economic stimulus as the plants buy fuel, supplies and services. Some of the benefits are highly localized, including employment and property taxes. One locality is already feeling the pinch: Oak Harbor on Lake Erie, home to Davis-Besse. The town has a middle school in a building that is 106 years old, and an elementary school from the 1950s, and on May 2 was scheduled to have a referendu

Why Ex-Im Bank Board Nominations Will Turn the Page on a Dysfunctional Chapter in Washington

In our present era of political discord, could Washington agree to support an agency that creates thousands of American jobs by enabling U.S. companies of all sizes to compete in foreign markets? What if that agency generated nearly billions of dollars more in revenue than the cost of its operations and returned that money – $7 billion over the past two decades – to U.S. taxpayers? In fact, that agency, the Export-Import Bank of the United States (Ex-Im Bank), was reauthorized by a large majority of Congress in 2015. To be sure, the matter was not without controversy. A bipartisan House coalition resorted to a rarely-used parliamentary maneuver in order to force a vote. But when Congress voted, Ex-Im Bank won a supermajority in the House and a large majority in the Senate. For almost two years, however, Ex-Im Bank has been unable to function fully because a single Senate committee chairman prevented the confirmation of nominees to its Board of Directors. Without a quorum

NEI Praises Connecticut Action in Support of Nuclear Energy

Earlier this week, Connecticut Gov. Dannel P. Malloy signed SB-1501 into law, legislation that puts nuclear energy on an equal footing with other non-emitting sources of energy in the state’s electricity marketplace. “Gov. Malloy and the state legislature deserve praise for their decision to support Dominion’s Millstone Power Station and the 1,500 Connecticut residents who work there," said NEI President and CEO Maria Korsnick. "By opening the door to Millstone having equal access to auctions open to other non-emitting sources of electricity, the state will help preserve $1.5 billion in economic activity, grid resiliency and reliability, and clean air that all residents of the state can enjoy," Korsnick said. Millstone Power Station Korsnick continued, "Connecticut is the third state to re-balance its electricity marketplace, joining New York and Illinois, which took their own legislative paths to preserving nuclear power plants in 2016. Now attention should